Question 82easy
What is another term for “perfect competition”?
Question 83hard
A person buys a piece of lot for P 100,000 downpayment and 10 deferred semi-annual payments of P 8,000 each, starting three years from now. What is the present value of the investment if the rate of interest is 12% compounded semi-annually?
Question 84hard
Mr. Jun Ramos was granted a loan of P20,000 by his employer Excel First Review and Training Center, Inc. with an interest of 6% for 180 days on the principal collected in advance. The corporation would accept a promissory note for P20,000 non-interest for 180 days. If discounted at once, find the proceeds of the note.
Advertisement
Question 85medium
What is the feature of some bonds whereby the issuer can redeem it before it matures?
Question 86medium
Present worth Annuity (PWA) is generally known as
Question 87hard
A leading shoe manufacturer produces a pair of Lebron James signature shoes at a labor cost of P 900.00 a pair and a material cost of P 800.00 a pair. The fixed charges on the business are P 5,000,000 a month and the variable costs are P 400.00 a pair. Royalty to Lebron James is P 1,000 per pair of shoes sold. If the shoes sell at P 5,000 a pair, how many pairs must be produced each month for the manufacturer to break-even?
Advertisement
Question 88medium
Duopsony is a market situation where there is/are:
Question 89medium
Duopoly is a market situation where there is/are:
Question 90hard
What is the present worth of two P 100 payments at the end of the third year and fourth year? The annual interest rate is 8%.